SANAO-1
Under Construction
Reactor Details
Reactor Type
|
Model
|
Owner
|
Operator
|
PWR
|
HRP1000
|
CGN Cangnan Nuclear Co.,Ltd
|
CGN Cangnan Nuclear Co.,Ltd
|
Reference Unit Power (Net Capacity)
|
Design Net Capacity
|
Gross Capacity
|
Thermal Capacity
|
1117
MWe
|
1117
MWe
|
1210
MWe
|
3180
MWt
|
Construction Start Date
|
First Criticality Date
|
|
|
31 Dec, 2020
|
N/A
|
|
|
First Grid Connection
|
Commercial Operation Date
|
|
|
N/A
|
N/A
|
|
|
|
|