FUQING-2

Operational


Reactor Details

Reactor Type Model Owner Operator
PWR
CNP-1000
CNNC Fujian Fuqing Nuclear Power Co., LTD
CNNC Fujian Fuqing Nuclear Power Co., LTD
Reference Unit Power (Net Capacity) Design Net Capacity Gross Capacity Thermal Capacity
1000 MWe
1000 MWe
1089 MWe
2905 MWt
Construction Start Date First Criticality Date
17 Jun, 2009
22 Jul, 2015
First Grid Connection Commercial Operation Date
06 Aug, 2015
16 Oct, 2015

LifeTime Performance

Electricity Supplied Energy Availability Factor Operation Factor Energy Unavailability Factor Load Factor
22.75 TW.h
85.1 %
84.7 %
14.9 %
79.3 %
Lifetime performance calculated up to year 2018

Operating History

Year Electricity Supplied
[GW.h]
Reference Unit Power
[MW]
Annual Time On Line
[h]
Operation Factor
[%]
Energy Availability Factor
[%]
Load Factor
[%]
Annual Cumulative Annual Cumulative
2015 2017.220 1000 3487 100.0 100.0 100.0 87.8 87.8
2016 6070.840 1000 6807 77.5 81.5 84.1 69.1 71.8
2017 7416.830 1000 7659 87.4 86.6 85.2 84.7 77.7
2018 7255.870 1000 7587 86.6 84.8 85.1 82.8 79.3
Performance indicators are calculated from the Commercial Operation Date.


Above data are from the PRIS database. Last update on 2019-12-12

Previous  (FUQING-1) (FUQING-3)  Next