TAISHAN-1

Operational


Reactor Details

Reactor Type Model Owner Operator
PWR
EPR-1750
Taishan Nuclear Power Joint Venture Company Limited
Taishan Nuclear Power Joint Venture Company Limited
Reference Unit Power (Net Capacity) Design Net Capacity Gross Capacity Thermal Capacity
1660 MWe
1660 MWe
1750 MWe
4590 MWt
Construction Start Date First Criticality Date
18 Nov, 2009
06 Jun, 2018
First Grid Connection Commercial Operation Date
29 Jun, 2018
13 Dec, 2018

LifeTime Performance

Electricity Supplied Energy Availability Factor Operation Factor Energy Unavailability Factor Load Factor
37.92 TW.h
52.5 %
55.6 %
47.5 %
48.6 %
Lifetime performance calculated up to year 2023

Operating History

Year Electricity Supplied
[GW.h]
Reference Unit Power
[MW]
Annual Time On Line
[h]
Operation Factor
[%]
Energy Availability Factor
[%]
Load Factor
[%]
Annual Cumulative Annual Cumulative
2018 3056.090 1660 3958 100.0 84.5 84.5 83.5 83.5
2019 11952.730 1660 7836 89.4 90.8 90.3 82.2 82.3
2020 9169.830 1660 6377 72.6 70.5 80.8 62.9 73.0
2021 7616.680 1660 4933 56.3 55.1 72.5 52.4 66.3
2022 4113.090 1660 3322 37.9 28.3 61.7 28.3 57.0
2023 2068.270 1660 1545 17.6 15.2 52.5 14.2 48.6
Performance indicators are calculated from the Commercial Operation Date.


Above data generated by the PRIS database. Last update on 2024-09-18


Previous  (TAIPINGLING-2) (TAISHAN-2)  Next