XUDAPU-3

Under Construction


Reactor Details

Reactor Type Model Owner Operator
PWR
VVER-1200/V491
CHINA NATIONAL NUCLEAR CORPORATION
LIAONING NUCLEAR POWER COMPANY, LMT.
Reference Unit Power (Net Capacity) Design Net Capacity Gross Capacity Thermal Capacity
1200 MWe
1200 MWe
1274 MWe
3200 MWt
Construction Start Date First Criticality Date
28 Jul, 2021
N/A
First Grid Connection Commercial Operation Date
N/A
N/A


Above data generated by the PRIS database. Last update on 2024-12-04