LING AO-1
Operational
Reactor Details
Reactor Type
|
Model
|
Owner
|
Operator
|
PWR
|
M310
|
LINGAO NUCLEAR POWER COMPANY LTD.
|
Daya Bay Nuclear Power Operations and Management Co, Ltd.
|
Reference Unit Power (Net Capacity)
|
Design Net Capacity
|
Gross Capacity
|
Thermal Capacity
|
950
MWe
|
950
MWe
|
990
MWe
|
2905
MWt
|
Construction Start Date
|
First Criticality Date
|
|
|
15 May, 1997
|
04 Feb, 2002
|
|
|
First Grid Connection
|
Commercial Operation Date
|
|
|
26 Feb, 2002
|
28 May, 2002
|
|
|
|
|
LifeTime Performance
Electricity Supplied
|
Energy Availability Factor
|
Operation Factor
|
Energy Unavailability Factor
|
Load Factor
|
150.19 TW.h
|
89.5 %
|
90.3 %
|
10.5 %
|
87.9 %
|
Lifetime performance calculated up to year
2022
Operating History
Year
|
Electricity Supplied
[GW.h]
|
Reference Unit Power
[MW]
|
Annual Time On Line
[h]
|
Operation Factor
[%]
|
Energy Availability Factor
[%]
|
Load Factor
[%]
|
Annual
|
Cumulative
|
Annual
|
Cumulative
|
2002
|
4583.850
|
938
|
5184
|
99.5
|
95.1
|
95.1
|
93.5
|
93.5
|
2003
|
6375.050
|
938
|
7215
|
82.4
|
80.4
|
85.8
|
77.6
|
83.5
|
2004
|
7331.360
|
938
|
7884
|
89.8
|
88.7
|
86.9
|
89.0
|
85.6
|
2005
|
6906.430
|
938
|
7424
|
84.8
|
84.3
|
86.2
|
84.0
|
85.2
|
2006
|
7401.010
|
938
|
7964
|
90.9
|
90.1
|
87.0
|
90.1
|
86.2
|
2007
|
6835.040
|
938
|
7345
|
83.8
|
83.2
|
86.4
|
83.2
|
85.7
|
2008
|
7542.850
|
938
|
8163
|
92.9
|
91.2
|
87.1
|
91.6
|
86.6
|
2009
|
7002.520
|
938
|
7997
|
91.3
|
90.4
|
87.5
|
85.2
|
86.4
|
2010
|
7714.570
|
938
|
8288
|
94.6
|
93.6
|
88.2
|
93.9
|
87.3
|
2011
|
7571.370
|
938
|
8072
|
92.2
|
91.2
|
88.5
|
92.1
|
87.8
|
2012
|
7657.290
|
938
|
8286
|
94.3
|
93.4
|
89.0
|
92.9
|
88.3
|
2013
|
6841.690
|
950
|
7340
|
83.8
|
82.5
|
88.4
|
82.3
|
87.8
|
2014
|
7361.900
|
950
|
7899
|
90.2
|
89.4
|
88.5
|
88.5
|
87.8
|
2015
|
7180.100
|
950
|
7656
|
87.4
|
86.8
|
88.4
|
86.3
|
87.7
|
2016
|
8253.130
|
950
|
8784
|
100.0
|
99.7
|
89.2
|
98.9
|
88.5
|
2017
|
7020.490
|
950
|
7538
|
86.0
|
88.6
|
89.1
|
84.4
|
88.2
|
2018
|
6990.810
|
950
|
7667
|
87.5
|
86.5
|
89.0
|
84.0
|
88.0
|
2019
|
7518.480
|
950
|
8363
|
95.5
|
94.7
|
89.3
|
90.3
|
88.1
|
2020
|
7556.540
|
950
|
8784
|
100.0
|
100.0
|
89.9
|
90.6
|
88.2
|
2021
|
7441.920
|
950
|
7896
|
90.1
|
89.4
|
89.8
|
89.4
|
88.3
|
2022
|
6706.960
|
950
|
7226
|
82.5
|
82.0
|
89.5
|
80.6
|
87.9
|
Performance indicators are calculated from the Commercial Operation Date.
Above data generated by the PRIS database. Last update on 2023-06-04