HAIYANG-2

Operational


Reactor Details

Reactor Type Model Owner Operator
PWR
AP-1000
China Power Investment Corporation
Shandong Nuclear Power Company, Ltd.
Reference Unit Power (Net Capacity) Design Net Capacity Gross Capacity Thermal Capacity
1170 MWe
1126 MWe
1250 MWe
3415 MWt
Construction Start Date First Criticality Date
20 Jun, 2010
29 Sep, 2018
First Grid Connection Commercial Operation Date
13 Oct, 2018
09 Jan, 2019

LifeTime Performance

Electricity Supplied Energy Availability Factor Operation Factor Energy Unavailability Factor Load Factor
10.74 TW.h
97.4 %
99.4 %
2.6 %
96.9 %
Lifetime performance calculated up to year 2019

Operating History

Year Electricity Supplied
[GW.h]
Reference Unit Power
[MW]
Annual Time On Line
[h]
Operation Factor
[%]
Energy Availability Factor
[%]
Load Factor
[%]
Annual Cumulative Annual Cumulative
2018 800.720 1170 1099
2019 9935.220 1170 8711 99.4 97.4 97.4 96.9 96.9
Performance indicators are calculated from the Commercial Operation Date.


Above data are from the PRIS database. Last update on 2020-05-24

Previous  (HAIYANG-1) (HONGYANHE-1)  Next