Armenia
Summary
IN OPERATION
MW(e) TOTAL NET CAPACITY
NUCLEAR POWER REACTORS
|
UNDER CONSTRUCTION
MW(e) TOTAL NET CAPACITY
NUCLEAR POWER REACTORS
|
PERMANENT SHUTDOWN
MW(e) TOTAL NET CAPACITY
NUCLEAR POWER REACTORS
|
|
|
ELECTRICITY PRODUCTION SHARE IN 2022
2 631 GWh ELECTRICITY SUPPLIED
Reactors
Name
|
Type
|
Status
|
Location
|
Reference Unit Power
[MW]
|
Gross Electrical Capacity
[MW]
|
First Grid Connection
|
ARMENIAN-1
|
PWR
|
Permanent Shutdown
|
METSAMOR
|
376
|
408
|
1976-12-22
|
ARMENIAN-2
|
PWR
|
Operational
|
METSAMOR
|
416
|
448
|
1980-01-05
|
Above data generated by the PRIS database. Last update on 2023-12-02