Mexico
Summary
IN OPERATION
MW(e) TOTAL NET CAPACITY
NUCLEAR POWER REACTORS
|
UNDER CONSTRUCTION
MW(e) TOTAL NET CAPACITY
NUCLEAR POWER REACTORS
|
PERMANENT SHUTDOWN
MW(e) TOTAL NET CAPACITY
NUCLEAR POWER REACTORS
|
|
|
ELECTRICITY PRODUCTION SHARE IN 2022
10 539 GWh ELECTRICITY SUPPLIED
Reactors
Name
|
Type
|
Status
|
Location
|
Reference Unit Power
[MW]
|
Gross Electrical Capacity
[MW]
|
First Grid Connection
|
LAGUNA VERDE-1
|
BWR
|
Operational
|
ALTO LUCERO
|
777
|
805
|
1989-04-12
|
LAGUNA VERDE-2
|
BWR
|
Operational
|
ALTO LUCERO
|
775
|
803
|
1994-11-11
|
Above data generated by the PRIS database. Last update on 2023-10-02