Russian Federation
Summary
IN OPERATION
MW(e) TOTAL NET CAPACITY
NUCLEAR POWER REACTORS
|
UNDER CONSTRUCTION
MW(e) TOTAL NET CAPACITY
NUCLEAR POWER REACTORS
|
PERMANENT SHUTDOWN
MW(e) TOTAL NET CAPACITY
NUCLEAR POWER REACTORS
|
|
|
ELECTRICITY PRODUCTION SHARE IN 2022
223 372 GWh ELECTRICITY SUPPLIED
Reactors
Name
|
Type
|
Status
|
Location
|
Reference Unit Power
[MW]
|
Gross Electrical Capacity
[MW]
|
First Grid Connection
|
APS-1 OBNINSK
|
LWGR
|
Permanent Shutdown
|
OBNINSK
|
5
|
6
|
1954-06-27
|
BALAKOVO-1
|
PWR
|
Operational
|
BALAKOVO
|
950
|
1000
|
1985-12-28
|
BALAKOVO-2
|
PWR
|
Operational
|
BALAKOVO
|
950
|
1000
|
1987-10-08
|
BALAKOVO-3
|
PWR
|
Operational
|
BALAKOVO
|
950
|
1000
|
1988-12-25
|
BALAKOVO-4
|
PWR
|
Operational
|
BALAKOVO
|
950
|
1000
|
1993-04-11
|
BELOYARSK-4
|
FBR
|
Operational
|
ZARECHNYY
|
820
|
885
|
2015-12-10
|
BELOYARSK-3
|
FBR
|
Operational
|
ZARECHNYY
|
560
|
600
|
1980-04-08
|
BELOYARSK-1
|
LWGR
|
Permanent Shutdown
|
ZARECHNYY
|
102
|
108
|
1964-04-26
|
BELOYARSK-2
|
LWGR
|
Permanent Shutdown
|
ZARECHNYY
|
146
|
160
|
1967-12-29
|
BILIBINO-1
|
LWGR
|
Permanent Shutdown
|
Bilibino
|
11
|
12
|
1974-01-12
|
BILIBINO-2
|
LWGR
|
Operational
|
Bilibino
|
11
|
12
|
1974-12-30
|
BILIBINO-3
|
LWGR
|
Operational
|
Bilibino
|
11
|
12
|
1975-12-22
|
BILIBINO-4
|
LWGR
|
Operational
|
Bilibino
|
11
|
12
|
1976-12-27
|
KALININ-1
|
PWR
|
Operational
|
UDOMLYA
|
950
|
1000
|
1984-05-09
|
KALININ-2
|
PWR
|
Operational
|
UDOMLYA
|
950
|
1000
|
1986-12-03
|
KALININ-3
|
PWR
|
Operational
|
UDOMLYA
|
950
|
1000
|
2004-12-16
|
KALININ-4
|
PWR
|
Operational
|
UDOMLYA
|
950
|
1000
|
2011-11-24
|
KOLA-1
|
PWR
|
Operational
|
POLYARNYYE ZORI
|
411
|
440
|
1973-06-29
|
KOLA-2
|
PWR
|
Operational
|
POLYARNYYE ZORI
|
411
|
440
|
1974-12-09
|
KOLA-3
|
PWR
|
Operational
|
POLYARNYYE ZORI
|
411
|
440
|
1981-03-24
|
KOLA-4
|
PWR
|
Operational
|
POLYARNYYE ZORI
|
411
|
440
|
1984-10-11
|
KURSK 2-1
|
PWR
|
Under Construction
|
KURCHATOV
|
1200
|
1255
|
|
KURSK-1
|
LWGR
|
Permanent Shutdown
|
KURCHATOV
|
925
|
1000
|
1976-12-19
|
KURSK 2-2
|
PWR
|
Under Construction
|
KURCHATOV
|
1200
|
1255
|
|
KURSK-2
|
LWGR
|
Operational
|
KURCHATOV
|
925
|
1000
|
1979-01-28
|
KURSK-3
|
LWGR
|
Operational
|
KURCHATOV
|
925
|
1000
|
1983-10-17
|
KURSK-4
|
LWGR
|
Operational
|
KURCHATOV
|
925
|
1000
|
1985-12-02
|
LENINGRAD-1
|
LWGR
|
Permanent Shutdown
|
SOSNOVYY BOR
|
925
|
1000
|
1973-12-21
|
LENINGRAD-2
|
LWGR
|
Permanent Shutdown
|
SOSNOVYY BOR
|
925
|
1000
|
1975-07-11
|
LENINGRAD 2-1
|
PWR
|
Operational
|
SOSNOVYY BOR
|
1101
|
1188
|
2018-03-09
|
LENINGRAD 2-2
|
PWR
|
Operational
|
SOSNOVYY BOR
|
1101
|
1188
|
2020-10-22
|
LENINGRAD-3
|
LWGR
|
Operational
|
SOSNOVYY BOR
|
925
|
1000
|
1979-12-07
|
LENINGRAD-4
|
LWGR
|
Operational
|
SOSNOVYY BOR
|
925
|
1000
|
1981-02-09
|
NOVOVORONEZH-4
|
PWR
|
Operational
|
NOVOVORONEZH
|
385
|
417
|
1972-12-28
|
NOVOVORONEZH-5
|
PWR
|
Operational
|
NOVOVORONEZH
|
950
|
1000
|
1980-05-31
|
NOVOVORONEZH-1
|
PWR
|
Permanent Shutdown
|
NOVOVORONEZH
|
197
|
210
|
1964-09-30
|
NOVOVORONEZH-2
|
PWR
|
Permanent Shutdown
|
NOVOVORONEZH
|
336
|
365
|
1969-12-27
|
NOVOVORONEZH-3
|
PWR
|
Permanent Shutdown
|
NOVOVORONEZH
|
385
|
417
|
1971-12-27
|
NOVOVORONEZH 2-1
|
PWR
|
Operational
|
NOVOVORONEZH
|
1100
|
1180
|
2016-08-05
|
NOVOVORONEZH 2-2
|
PWR
|
Operational
|
NOVOVORONEZH
|
1101
|
1181
|
2019-05-01
|
AKADEMIK LOMONOSOV-1
|
PWR
|
Operational
|
PEVEK
|
32
|
35
|
2019-12-19
|
AKADEMIK LOMONOSOV-2
|
PWR
|
Operational
|
PEVEK
|
32
|
35
|
2019-12-19
|
BREST-OD-300
|
FBR
|
Under Construction
|
SEVERSK
|
300
|
320
|
|
SMOLENSK-1
|
LWGR
|
Operational
|
DESNOGORSK
|
925
|
1000
|
1982-12-09
|
SMOLENSK-2
|
LWGR
|
Operational
|
DESNOGORSK
|
925
|
1000
|
1985-05-31
|
SMOLENSK-3
|
LWGR
|
Operational
|
DESNOGORSK
|
925
|
1000
|
1990-01-17
|
ROSTOV-1
|
PWR
|
Operational
|
VOLGODONSK
|
989
|
1041
|
2001-03-30
|
ROSTOV-2
|
PWR
|
Operational
|
VOLGODONSK
|
950
|
1000
|
2010-03-18
|
ROSTOV-3
|
PWR
|
Operational
|
VOLGODONSK
|
950
|
1000
|
2014-12-27
|
ROSTOV-4
|
PWR
|
Operational
|
VOLGODONSK
|
979
|
1030
|
2018-02-02
|
Above data generated by the PRIS database. Last update on 2023-12-02