KAKRAPAR-4

Operational


Reactor Details

Reactor Type Model Owner Operator
PHWR
PHWR-700
NUCLEAR POWER CORPORATION OF INDIA, LTD.
NUCLEAR POWER CORPORATION OF INDIA, LTD.
Reference Unit Power (Net Capacity) Design Net Capacity Gross Capacity Thermal Capacity
630 MWe
630 MWe
700 MWe
2166 MWt
Construction Start Date First Criticality Date
22 Nov, 2010
17 Dec, 2023
First Grid Connection Commercial Operation Date
20 Feb, 2024
31 Mar, 2024

LifeTime Performance

Electricity Supplied Energy Availability Factor Operation Factor Energy Unavailability Factor Load Factor
NC
NC
NC
NC
NC
Lifetime performance calculated up to year 2022

Operating History

Year Electricity Supplied
[GW.h]
Reference Unit Power
[MW]
Annual Time On Line
[h]
Operation Factor
[%]
Energy Availability Factor
[%]
Load Factor
[%]
Annual Cumulative Annual Cumulative
Performance indicators are calculated from the Commercial Operation Date.
NC – cumulative values not calculated when more than 50% of required data is missing in PRIS


Above data generated by the PRIS database. Last update on 2024-11-03