BARAKAH-4

Operational


Reactor Details

Reactor Type Model Owner Operator
PWR
APR-1400
Emirates Nuclear Energy Corporation
Nawah Energy Company
Reference Unit Power (Net Capacity) Design Net Capacity Gross Capacity Thermal Capacity
1337 MWe
1310 MWe
1417 MWe
3983 MWt
Construction Start Date First Criticality Date
30 Jul, 2015
01 Mar, 2024
First Grid Connection Commercial Operation Date
23 Mar, 2024
05 Sep, 2024

LifeTime Performance

Electricity Supplied Energy Availability Factor Operation Factor Energy Unavailability Factor Load Factor
5.12 TW.h
83.0 %
89.8 %
17.0 %
83.7 %
Lifetime performance calculated up to year 2024

Operating History

Year Electricity Supplied
[GW.h]
Reference Unit Power
[MW]
Annual Time On Line
[h]
Operation Factor
[%]
Energy Availability Factor
[%]
Load Factor
[%]
Annual Cumulative Annual Cumulative
2024 5119.360 1337 4886 89.8 83.0 83.0 83.7 83.7
Performance indicators are calculated from the Commercial Operation Date.


Above data generated by the PRIS database. Last update on 2026-01-17