XUDAPU-2

Under Construction


Reactor Details

Reactor Type Model Owner Operator
PWR
CAP1000
CHINA NATIONAL NUCLEAR CORPORATION
LIAONING NUCLEAR POWER COMPANY, LMT.
Reference Unit Power (Net Capacity) Design Net Capacity Gross Capacity Thermal Capacity
1000 MWe
1000 MWe
1290 MWe
2905 MWt
Construction Start Date First Criticality Date
17 Jul, 2024
N/A
First Grid Connection Commercial Operation Date
N/A
N/A


Above data generated by the PRIS database. Last update on 2024-11-03


Previous  (XUDAPU-1) (XUDAPU-3)  Next