MUELHEIM-KAERLICH
(KMK)
Permanent Shutdown
Reactor Details
Reactor Type
Model
Owner
Operator
PWR
PWR
SCN
Kernkraftwerk Gundremmingen GmbH
Reference Unit Power (Net Capacity)
Design Net Capacity
Gross Capacity
Thermal Capacity
1219
MW
e
1219
MW
e
1302
MW
e
3760
MW
t
Construction Start Date
First Criticality Date
15 Jan, 1975
01 Mar, 1986
First Grid Connection
Commercial Operation Date
14 Mar, 1986
18 Aug, 1987
Permanent Shutdown Date
09 Sep, 1988
LifeTime Performance
Electricity Supplied
Energy Availability Factor
Operation Factor
Energy Unavailability Factor
Load Factor
10.29 TW.h
94.7 %
76.0 %
5.3 %
76.4 %
Lifetime performance calculated up to year
1988
Operating History
Year
Electricity Supplied
[GW.h]
Reference Unit Power
[MW]
Annual Time On Line
[h]
Operation Factor
[%]
Energy Availability Factor
[%]
Load Factor
[%]
Annual
Cumulative
Annual
Cumulative
1986
1357.590
1165
0
1987
2904.300
1165
1564
42.6
92.9
92.9
67.9
67.9
1988
6029.360
1219
5884
96.9
95.7
94.7
81.5
76.4
Performance indicators are calculated from the Commercial Operation Date.
Above data generated by the PRIS database. Last update on 2024-10-03
Previous
(LINGEN)
(MZFR)
Next
GERMANY
AVR JUELICH
BIBLIS-A
BIBLIS-B
BROKDORF
BRUNSBUETTEL
EMSLAND
GRAFENRHEINFELD
GREIFSWALD-1
GREIFSWALD-2
GREIFSWALD-3
GREIFSWALD-4
GREIFSWALD-5
GROHNDE
GUNDREMMINGEN-A
GUNDREMMINGEN-B
GUNDREMMINGEN-C
HDR GROSSWELZHEIM
ISAR-1
ISAR-2
KNK II
KRUEMMEL
LINGEN
MUELHEIM-KAERLICH
MZFR
NECKARWESTHEIM-1
NECKARWESTHEIM-2
NIEDERAICHBACH
OBRIGHEIM
PHILIPPSBURG-1
PHILIPPSBURG-2
RHEINSBERG
STADE
THTR-300
UNTERWESER
VAK KAHL
WUERGASSEN