AKADEMIK LOMONOSOV-1
Operational
Reactor Details
Reactor Type
Model
Owner
Operator
PWR
KLT-40S 'Floating'
Joint Stock Company 'Concern Rosenergoatom'
Joint Stock Company 'Concern Rosenergoatom'
Reference Unit Power (Net Capacity)
Design Net Capacity
Gross Capacity
Thermal Capacity
32
MW
e
30
MW
e
35
MW
e
150
MW
t
Construction Start Date
First Criticality Date
15 Apr, 2007
02 Nov, 2018
First Grid Connection
Commercial Operation Date
19 Dec, 2019
22 May, 2020
LifeTime Performance
Electricity Supplied
Energy Availability Factor
Operation Factor
Energy Unavailability Factor
Load Factor
0.34 TW.h
61.7 %
71.0 %
38.3 %
32.0 %
Lifetime performance calculated up to year
2023
Operating History
Year
Electricity Supplied
[GW.h]
Reference Unit Power
[MW]
Annual Time On Line
[h]
Operation Factor
[%]
Energy Availability Factor
[%]
Load Factor
[%]
Annual
Cumulative
Annual
Cumulative
2019
0.680
32
312
2020
64.930
32
5138
71.6
90.4
90.4
28.8
28.8
2021
125.260
32
7104
81.1
85.1
87.0
44.7
38.8
2022
74.130
32
6367
72.7
50.0
72.7
26.4
34.0
2023
74.630
32
5143
58.7
33.0
61.7
26.6
32.0
Performance indicators are calculated from the Commercial Operation Date.
Above data generated by the PRIS database. Last update on 2024-10-03
Previous
(SMOLENSK-3)
(AKADEMIK LOMONOSOV-2)
Next
RUSSIA
AKADEMIK LOMONOSOV-1
AKADEMIK LOMONOSOV-2
APS-1 OBNINSK
BALAKOVO-1
BALAKOVO-2
BALAKOVO-3
BALAKOVO-4
BELOYARSK-1
BELOYARSK-2
BELOYARSK-3
BELOYARSK-4
BILIBINO-1
BILIBINO-2
BILIBINO-3
BILIBINO-4
BREST-OD-300
KALININ-1
KALININ-2
KALININ-3
KALININ-4
KOLA-1
KOLA-2
KOLA-3
KOLA-4
KURSK 2-1
KURSK 2-2
KURSK-1
KURSK-2
KURSK-3
KURSK-4
LENINGRAD 2-1
LENINGRAD 2-2
LENINGRAD 2-3
LENINGRAD-1
LENINGRAD-2
LENINGRAD-3
LENINGRAD-4
NOVOVORONEZH 2-1
NOVOVORONEZH 2-2
NOVOVORONEZH-1
NOVOVORONEZH-2
NOVOVORONEZH-3
NOVOVORONEZH-4
NOVOVORONEZH-5
ROSTOV-1
ROSTOV-2
ROSTOV-3
ROSTOV-4
SMOLENSK-1
SMOLENSK-2
SMOLENSK-3