SAEUL-1

Operational


Reactor Details

Reactor Type Model Owner Operator
PWR
APR-1400
Korea Hydro and Nuclear Power Co.
Korea Hydro and Nuclear Power Co.
Reference Unit Power (Net Capacity) Design Net Capacity Gross Capacity Thermal Capacity
1392 MWe
1340 MWe
1488 MWe
3983 MWt
Construction Start Date First Criticality Date
16 Oct, 2008
29 Dec, 2015
First Grid Connection Commercial Operation Date
15 Jan, 2016
20 Dec, 2016

LifeTime Performance

Electricity Supplied Energy Availability Factor Operation Factor Energy Unavailability Factor Load Factor
71.65 TW.h
79.2 %
80.0 %
20.8 %
79.2 %
Lifetime performance calculated up to year 2023

Operating History

Year Electricity Supplied
[GW.h]
Reference Unit Power
[MW]
Annual Time On Line
[h]
Operation Factor
[%]
Energy Availability Factor
[%]
Load Factor
[%]
Annual Cumulative Annual Cumulative
2016 2851.250 1383 2956
2017 12405.610 1416 8760 100.0 99.8 99.8 100.0 100.0
2018 6027.000 1416 4360 49.8 48.6 74.2 48.6 74.3
2019 10939.060 1416 7762 88.6 88.1 78.8 88.2 78.9
2020 8544.980 1416 6120 69.7 68.8 76.3 68.7 76.4
2021 9400.370 1416 6706 76.6 75.8 76.2 75.8 76.2
2022 12328.840 1416 8760 100.0 99.3 80.0 99.4 80.1
2023 9154.980 1416 6587 75.2 74.2 79.2 73.8 79.2
Performance indicators are calculated from the Commercial Operation Date.


Above data generated by the PRIS database. Last update on 2025-01-25