NOVOVORONEZH-2

Permanent Shutdown


Reactor Details

Reactor Type Model Owner Operator
PWR
VVER V-365
MINISTRY OF MEDIUM MACHINE BUILDING OF THE USSR (MINSREDMASH)
Joint Stock Company 'Concern Rosenergoatom'
Reference Unit Power (Net Capacity) Design Net Capacity Gross Capacity Thermal Capacity
336 MWe
336 MWe
365 MWe
1320 MWt
Construction Start Date First Criticality Date
01 Jun, 1964
23 Dec, 1969
First Grid Connection Commercial Operation Date
27 Dec, 1969
14 Apr, 1970
Permanent Shutdown Date
29 Aug, 1990

LifeTime Performance

Electricity Supplied Energy Availability Factor Operation Factor Energy Unavailability Factor Load Factor
49.91 TW.h
NC
NC
NC
NC
Lifetime performance calculated up to year 1990

Operating History

Year Electricity Supplied
[GW.h]
Reference Unit Power
[MW]
Annual Time On Line
[h]
Operation Factor
[%]
Energy Availability Factor
[%]
Load Factor
[%]
Annual Cumulative Annual Cumulative
1969 Data from a trial operation not provided
1970 Data Not Provided
1971 "
1972 "
1973 "
1974 "
1975 "
1976 "
1977 "
1978 "
1979 "
1980 "
1981 "
1982 "
1983 "
1984 "
1985 "
1986 "
1987 2370.160 365 7167 81.8 80.1 NC 74.1 NC
1988 1998.640 336 6897 78.5 71.4 NC 67.7 NC
1989 2252.870 336 8157 93.1 85.1 NC 76.5 NC
1990 123.780 336 550 9.6 9.5 NC 6.4 NC
Performance indicators are calculated from the Commercial Operation Date.
NC – cumulative values not calculated when more than 50% of required data is missing in PRIS


Above data generated by the PRIS database. Last update on 2024-09-10

Previous  (NOVOVORONEZH-1) (NOVOVORONEZH-3)  Next