ROSTOV-4

Operational


Reactor Details

Reactor Type Model Owner Operator
PWR
VVER V-320
Joint Stock Company 'Concern Rosenergoatom'
Joint Stock Company 'Concern Rosenergoatom'
Reference Unit Power (Net Capacity) Design Net Capacity Gross Capacity Thermal Capacity
950 MWe
950 MWe
1030 MWe
3000 MWt
Construction Start Date First Criticality Date
16 Jun, 2010
29 Dec, 2017
First Grid Connection Commercial Operation Date
02 Feb, 2018
28 Sep, 2018

LifeTime Performance

Electricity Supplied Energy Availability Factor Operation Factor Energy Unavailability Factor Load Factor
5.68 TW.h
100.0 %
100.0 %
0.0 %
103.8 %
Lifetime performance calculated up to year 2018

Operating History

Year Electricity Supplied
[GW.h]
Reference Unit Power
[MW]
Annual Time On Line
[h]
Operation Factor
[%]
Energy Availability Factor
[%]
Load Factor
[%]
Annual Cumulative Annual Cumulative
2018 5681.920 950 6556 100.0 100.0 100.0 103.8 103.8
Performance indicators are calculated from the Commercial Operation Date.


Above data are from the PRIS database. Last update on 2019-10-22

Previous  (ROSTOV-3) (SMOLENSK-1)  Next