HANUL-6

Operational


Reactor Details

Reactor Type Model Owner Operator
PWR
OPR-1000
Korea Hydro and Nuclear Power Co.
Korea Hydro and Nuclear Power Co.
Reference Unit Power (Net Capacity) Design Net Capacity Gross Capacity Thermal Capacity
997 MWe
950 MWe
1049 MWe
2825 MWt
Construction Start Date First Criticality Date
29 Sep, 2000
16 Dec, 2004
First Grid Connection Commercial Operation Date
07 Jan, 2005
22 Apr, 2005

LifeTime Performance

Electricity Supplied Energy Availability Factor Operation Factor Energy Unavailability Factor Load Factor
145.57 TW.h
88.5 %
89.0 %
11.5 %
88.6 %
Lifetime performance calculated up to year 2023

Operating History

Year Electricity Supplied
[GW.h]
Reference Unit Power
[MW]
Annual Time On Line
[h]
Operation Factor
[%]
Energy Availability Factor
[%]
Load Factor
[%]
Annual Cumulative Annual Cumulative
2005 6010.960 960 6041 99.1 98.8 98.8 102.6 102.6
2006 7409.910 991 7543 86.1 86.6 91.4 85.4 92.2
2007 7911.300 994 8022 91.6 90.9 91.2 90.9 91.7
2008 8107.890 1001 8168 93.0 92.6 91.6 92.2 91.8
2009 8694.520 1001 8724 99.6 99.5 93.3 99.2 93.4
2010 7991.040 997 8055 92.0 91.4 93.0 91.5 93.1
2011 8090.560 997 8168 93.2 92.5 92.9 92.6 93.0
2012 7703.150 997 7763 88.4 87.8 92.2 88.0 92.3
2013 8716.350 996 8760 100.0 99.8 93.1 99.9 93.2
2014 7734.990 997 7810 89.2 88.5 92.6 88.6 92.7
2015 6465.700 997 6545 74.7 74.0 90.9 74.0 91.0
2016 8765.470 997 8784 100.0 99.8 91.6 100.1 91.8
2017 6830.580 997 6928 79.1 78.2 90.6 78.2 90.7
2018 7343.970 997 7419 84.7 84.1 90.1 84.1 90.2
2019 6739.280 997 6843 78.1 77.1 89.2 77.2 89.3
2020 6559.040 997 6607 75.2 74.8 88.3 74.9 88.4
2021 8708.440 997 8760 100.0 99.7 89.0 99.7 89.1
2022 7496.120 997 7620 87.0 85.8 88.8 85.8 88.9
2023 7214.720 997 7326 83.6 82.6 88.5 82.6 88.6
Performance indicators are calculated from the Commercial Operation Date.


Above data generated by the PRIS database. Last update on 2024-09-18


Previous  (HANUL-5) (KORI-1)  Next