GREIFSWALD-2 (KGR 2)

Permanent Shutdown


Reactor Details

Reactor Type Model Owner Operator
PWR
VVER V-230
ENERGIEWERKE Nord GmbH
ENERGIEWERKE Nord GmbH
Reference Unit Power (Net Capacity) Design Net Capacity Gross Capacity Thermal Capacity
408 MWe
408 MWe
440 MWe
1375 MWt
Construction Start Date First Criticality Date
01 Mar, 1970
03 Dec, 1974
First Grid Connection Commercial Operation Date
23 Dec, 1974
16 Apr, 1975
Permanent Shutdown Date
14 Feb, 1990

LifeTime Performance

Electricity Supplied Energy Availability Factor Operation Factor Energy Unavailability Factor Load Factor
36.57 TW.h
NC
NC
NC
NC
Lifetime performance calculated up to year 1989

Operating History

Year Electricity Supplied
[GW.h]
Reference Unit Power
[MW]
Annual Time On Line
[h]
Operation Factor
[%]
Energy Availability Factor
[%]
Load Factor
[%]
Annual Cumulative Annual Cumulative
1974 Data from a trial operation not provided
1975 Data Not Provided
1976 "
1977 "
1978 "
1979 "
1980 "
1981 "
1982 "
1983 "
1984 "
1985 "
1986 "
1987 "
1988 "
1989 2654.340 408 7452 85.1 73.4 NC 74.3 NC
1990 Data Not Provided
Performance indicators are calculated from the Commercial Operation Date.
NC – cumulative values not calculated when more than 50% of required data is missing in PRIS


Above data generated by the PRIS database. Last update on 2023-12-02

Previous  (GREIFSWALD-1) (GREIFSWALD-3)  Next